  1. After trusses are set, run two purlins to make sure the trusses are not pulled out of line.
  2. Attach TempShield® 48" Insulation to the first truss with at least 5/16" staples. Temporarily nail a 2"x 4" block to the truss to prevent metalized film from pulling away.
  3. Roll out the TempShield® across the trusses and pull the insulation tight.
  4. Install purlins over insulation. Nail or screw to trusses through insulation.
  5. Install the metal roof to purlins.

Wall Installation

  1. After main supports are installed, staple TempShield® 48" horizontally to the support beams.
  2. Install the 2"x 4" girts and the exterior corrugated metal.
  3. From inside the building, staple insulation to the girts.
  4. If an interior covering is called for, install either metal or wood sheets to the inside of the support beams. This will provide a 1-1/2" nominal airspace between the exterior metal and the insulation and a 5-1/4" nominal airspace between the insulation and the interior wall material.
Installer

Become a Dealer

Learn More
Guides

Installation Guides

Learn More
Sample

Request a Sample

Learn More

Contact Our Product Experts

Required Fields*

Have an inquiry? Have an inquiry?